Raise the question where it applies
Create a draft RFI with its subject, question and proposed solution, plus the discipline, location, drawing reference and specification reference it concerns. Record whether it may affect cost or schedule. Opening the RFI gives it a permanent project number such as RFI-001; without a due date, the default is seven business days after opening.
- Link the requirements, specifications and components it questions
- Attach photos, drawings and documents to the RFI or a response
- Each RFI counts as one artifact item; responses do not
Keep one responsible person
Ball in court is a single named person, starting with the RFI manager. Responders and watchers are separate lists. Replies, selecting an official answer and closing the RFI do not move responsibility; a writer reassigns it explicitly.
Invite responders by email
Assign a responder by email address. Existing project participants are assigned directly. Someone outside the project receives an ordinary TraceWorks invitation as a project Viewer, which lets them post shared replies without editing, approval, export, AI or MCP access.
A teammate can reply on behalf of someone else. The thread records the teammate as the author and names the person represented. To ask someone who should not join the workspace at all, use an external responder link.
Draft answers with AI, then review
The answer assistant can propose an answer from the project's indexed documents, requirements, specifications and earlier RFIs, with citations. When the evidence is insufficient it says so instead of drafting an engineering answer. Save the proposal as an internal draft, edit it, and share it only after you confirm you reviewed it.
- Confidence is a model estimate, not an engineering approval
- Retrieval is bounded and may miss relevant evidence
- Imported email threads are staged for review, never accepted automatically
Choose the official answer
A response alone does not answer the RFI. The RFI manager, a project Owner or an organization administrator selects one shared response as the official answer; an authorized writer can then close the RFI. Reopening and voiding both require a reason, and editing an issued question creates a new revision.
Turn the answer into a change
From the official answer, create a draft change order, a proposed decision, or a change request on an approved requirement. The traceability view lists the downstream records the linked items affect. Requirement changes enter the normal review queue; the approved baseline does not change until that request is approved.
PDFs, exports and reminders
Download an RFI as a project-record PDF, with or without its PDF attachments, or save it to the RFI's files as a new revision. The register exports to CSV and XLSX. PDF and register exports are included in Pro and Enterprise.
Managers, responsible people, responders and watchers receive lifecycle emails and reminders for overdue RFIs and RFIs due within two business days. Each person chooses which of these emails they receive. Open and overdue RFIs also show on the requirements, specifications and components they question, and in the coverage-gap report.